Capital Improvements Project | Projected Cost | Current Costs as of 05/31/2019 |
---|---|---|
Mortvedt Elevator | $246,628 | $217,009 |
Mortvedt Fire Alarm | $179,652 | $177,363 |
Nursing - Phase 3 (GBC) | $344,215 | $48,291 |
South Hall Boilers | $217,359 | $217,359 |
Ingram Classroom 109 | $103,967 | $84,441 |
Additional Contingency | $0.00 | $0.00 |
Total | $1,091,821 | $758,803 |